Refreshing a room completely

Refreshing a room is the ideal first project: no heavy breaking out, and you see the result straight away. The rule of thumb is to work from top to bottom and from dirty to clean. First the dusty work on the walls, then painting, then the floor, and the door and the lamps last.

Count on two to four weekends for a room of average size. Skip the phases you do not need.

6 steps, 10 jobs

The order of the work

Go through the steps from top to bottom. Every job has its own questionnaire, step-by-step plan and shopping lists.

  1. Step 1: Flattening the walls and ceiling

    Repair or renew the surface: plaster damaged walls or finish plasterboard until it is smooth. This is the dustiest work and therefore comes first. Let new plaster dry completely before you paint or paper.

  2. Step 2: Painting the woodwork

    Sand and paint the door frames, window sills and skirting boards that are staying. Woodwork comes before the walls: it is easier to cut a straight line with wall paint against the gloss than the other way round.

  3. Step 3: Painting or papering the walls and ceiling

    Paint the ceiling first and then the walls, or paper the walls. This comes before the floor, so that paint and paste fall on the old floor and not on the new one.

  4. Step 5: Fitting the interior door

    Hang the new door or trim the existing one. You do that after the floor, because the height of the new floor decides how much space has to stay under the door.

  5. Step 6: Lighting

    Finish with new lighting, for example LED strips or spotlights. Lamps come last, so they see no more dust or paint.